0817 - (Urgent) Treatment of Existing Capacity Holding at Easington on creation of the new Rough Storage ASEP

Last updated: 
4 July, 2023
Proposer
Centrica Energy Limited
Impacted codes
None
Modification type
Request
Status:
Implemented
 27/09/2022
Implementation date
Impact:
Low impact: National Gas Transmission, Shippers
High impact: Centrica Storage Limited

In response to the impending resumption of gas storage activities at Rough a new Rough Storage ASEP is being carved out of the Easington ASEP. This Modification proposal will ensure that existing capacity holdings at the Easington ASEP may be utilised at the Rough Storage ASEP.

Timeline

Raised
Yes
23/08/2022
Status

Date Modification Raised

Panel Assessment
Unset
31/08/2022
Status
Draft Modification Report issued for consultation
Workgroup Report Due
Unset
Consultation
Completed
31/08/2022
06/09/2022
Consultation - Final Modification Report
Yes
07/09/2022
Status

Final Modification Report available for Panel


Panel Decision
Yes
08/09/2022
Status

Modification Panel decision consideration / Modification sent to Ofgem

Implementation
Completed
28/09/2022