0818 - Releasing of unused capacity under a specific set of circumstances

Last updated: 
2 October, 2023
Proposer
Northern Gas Networks
Impacted codes
No other code impacts are identified (IGT CSEPs will be out of scope of this modification).
Modification type
Authority Direction
Status:
Rejected
 24/04/2023
Impact:
Medium impact: Suppliers
High impact: Consumers, Distribution Network Operators, Shippers

Occasionally capacity is booked but remains unused for years. This is only an issue for other Shippers and end consumers where there is limited capacity available on the same part of the system. This Modification is to release the unused capacity only where a site meets set specific criteria. This criteria is detailed and specific with a site having to meet all of the criteria for the modification to apply to them: The intent of which is that this modification will be limited to a small number of sites who it is believed are holding capacity they are not using, and have not used for at least 36 months; and where there is a genuine need by others for capacity but this is current unavailable because sites holding excess capacity.

Timeline

Raised
Yes
16/08/2022
Status

Date Modification Raised

Panel Assessment
Unset
16/09/2022
Status
New Modification to be considered by Panel
Workgroup Report Due
Yes
20/09/2022
Status

First Workgroup Meeting


Consultation
Completed
20/01/2023
10/02/2023
Consultation - Final Modification Report
Yes
19/01/2023
Status

Final Modification Report available for Panel


Panel Decision
Yes
19/03/2023
Status

Modification Panel decision

Implementation
Unset