Last updated:
15 March, 2024
Proposer
National Gas Transmission
Impacted codes
None
Modification type
Authority Direction
Status:
Implemented
Impact:
Low impact: Suppliers
High impact: Shippers
To enable the amendment of BBL’s Interconnector Agreement (IA) to temporarily provide for an enhanced pressure service for BBL at Bacton Exit Interconnection Point (IP) permitting BBL to request enhanced pressures between 55 bar and 68 bar when exporting gas at Bacton Interconnector and to increase its Maximum NTS Exit Point Offtake Rate (MNEPOR).
Timeline
Panel Assessment
Yes
27/07/2022
Status
Draft Modification Report issued for consultation
Draft Modification Report issued for consultation
Workgroup Report Due
Unset
Consultation
Completed
27/07/2022
01/08/2022
Consultation - Final Modification Report
Yes
02/08/2022
Status
Final Modification Report available for Panel
Panel Decision
Yes
03/08/2023
Status
Modification Panel decision consideration
Implementation
Completed
19/07/2023