0814 - (Urgent) - Temporary Access to the Enhanced Pressure Service and Increase to the Maximum NTS Exit Point Offtake Rate of the BBL interconnector

Last updated: 
15 March, 2024
Proposer
National Gas Transmission
Impacted codes
None
Modification type
Authority Direction
Status:
Implemented
Impact:
Low impact: Suppliers
High impact: Shippers

To enable the amendment of BBL’s Interconnector Agreement (IA) to temporarily provide for an enhanced pressure service for BBL at Bacton Exit Interconnection Point (IP) permitting BBL to request enhanced pressures between 55 bar and 68 bar when exporting gas at Bacton Interconnector and to increase its Maximum NTS Exit Point Offtake Rate (MNEPOR).

Timeline

Raised
Yes
22/07/2022
Status

Modification Raised

Panel Assessment
Yes
27/07/2022
Status
Draft Modification Report issued for consultation
Workgroup Report Due
Unset
Consultation
Completed
27/07/2022
01/08/2022
Consultation - Final Modification Report
Yes
02/08/2022
Status

Final Modification Report available for Panel


Panel Decision
Yes
03/08/2023
Status

Modification Panel decision consideration

Implementation
Completed
19/07/2023