Proposer
Steve Mulinganie
Modification type
Authority Direction
Status:
Implemented
01/07/2019
Implementation date
Impact:
High impact: CDSP, Distribution Network Operators, Rough Storage, Shippers
This Modification has 2 purposes:
- It amends the current Class 2 Ratchet Charging Arrangement
-It allows Transporters to identify Supply Points that should, in addition to mandatory Class 1 Supply Points, be subject to the existing Class 1 Ratchet Charging Arrangement
For the avoidance of doubt NTS Supply Points are excluded from the scope of this Modification
Timeline
Panel Assessment
Yes
28/02/2019
Status
Amended Modification consider by Workgroup
Amended Modification consider by Workgroup
Workgroup Report Due
Yes
01/03/2019
Status
Workgroup Report presented to Panel
Consultation
Completed
01/03/2019
14/03/2019
Consultation - Final Modification Report
Yes
15/03/2019
Status
Final Modification Report available for Panel
Panel Decision
Yes
21/03/2019
Status
Modification Panel decision
Implementation
Completed
01/07/2019