0634 (Urgent) - Revised estimation process for DM sites with D-7 zero consumption

Last updated: 
23 August, 2023
Proposer
Carl Whitehouse
Modification type
Urgent
Status:
Implemented
 16/11/2017
Implementation date
Impact:
Medium impact: GB Gas Transporters, Independent Gas Transporters
High impact: Shippers, Suppliers

This modification proposes to create a new process for amending daily metered consumption to prevent D-7 zero estimates from being used where inappropriate to do so

Timeline

Raised
Yes
27/10/2017
Status

Date Raised

Panel Assessment
Yes
13/10/2017
Status
Panel Recommendation on Urgency
Workgroup Report Due
Yes
16/10/2017
Status

Ofgem Decision on Urgency


Consultation
Completed
27/10/2017
03/11/2017
Consultation - Final Modification Report
Yes
06/11/2017
Status

Final Modification Report available for Panel


Panel Decision
Yes
09/11/2017
Status

Modification Panel decision

Implementation
Unset