0624R - Review of arrangements for Retrospective Adjustment of Meter Information, Meter Point/Supply Point and Address data

Last updated: 
14 February, 2024
Proposer
Chris Warner
Status:
Implemented
Impact:
Medium impact: CDSP, GB Gas Transporters, Independent Gas Transporters, Rough Storage, Shippers

To conduct a review of the elements of UNC Modification 0434 ‘Project Nexus – Retrospective Adjustment’ relating to the retrospective adjustment of Meter Information, Meter Point/Supply Point and Address data. This will be informed by undertaking a cost benefit assessment of the elements of the Modification which have not been implemented.

Timeline

Raised
Yes
10/07/2017
Status

Date raised

Panel Assessment
Yes
24/08/2017
Status
Initial consideration by Workgroup
Workgroup Report Due
Yes
15/02/2018
Status

Workgroup Report presented to Panel


Consultation
Unset
Consultation - Final Modification Report
Unset
Panel Decision
Yes
Status

Closed

Implementation
Unset