Last updated:
4 October, 2023
Proposer
Shell Energy Europe Limited
Impacted codes
None
Modification type
Request
Status:
Implemented
15/12/2022
Impact:
Low impact: Consumers, GB Gas Transporters, Shippers
This Modification will enable the current Wobbe Index upper limit that applies between National Grid and Shell at St Fergus to be temporarily increased from 51.2 MJ/m3 to 51.4 MJ/m3.
Timeline
Panel Assessment
Yes
20/10/2022
Status
New Modification to be considered by Panel
New Modification to be considered by Panel
Workgroup Report Due
Yes
20/10/2022
Status
New Modification to be considered by Panel
Consultation
Completed
24/10/2022
11/11/2022
Consultation - Final Modification Report
Yes
17/11/2022
Status
Final Modification Report available for Panel
Panel Decision
Yes
15/12/2022
Implementation
Completed
11/01/2023