0801 - Removal of capacity and balancing services from the role of CDSP

Last updated: 
4 July, 2023
Proposer
National Grid
Impacted codes
UNC.
Modification type
Authority Direction
Status:
Withdrawn
 01/07/2022
Impact:
High impact: CDSP

This Modification proposes to remove certain services, relating to capacity and balancing, from the role of the Central Data Service Provider (CDSP) within UNC. This will allow National Grid to deliver their UNC obligations through other means.

Timeline

Raised
Yes
04/02/2022
Status

Date Modification Raised

Panel Assessment
Yes
17/02/2022
Status
New Modification to be considered by Panel
Workgroup Report Due
Yes
03/03/2022
Status

First Workgroup Meeting


Consultation
Completed
19/05/2022
13/06/2022
Consultation - Final Modification Report
Yes
14/06/2022
Status

Final Modification Report available for Panel


Panel Decision
Yes
16/06/2022
Status

Modification Panel decision (at short notice)

Implementation
Unset