0798S - Enablement of Exit Assignment process at Interconnectors

Last updated: 
1 December, 2023
Proposer
National Grid
Impacted codes
Uniform Network Code (UNC), European Interconnection Document (EID)
Modification type
Self-Governance
Status:
Implemented
 24/04/2022
Implementation date

UNC Modification 0755S - Enhancement of Exit Capacity Assignments was approved for implementation on 15 July 2021. That Modification allowed for the application of the Assignment process to Unbundled Capacity at Interconnectors and is due to be implemented in Spring 2022. This Modification amends the European Interconnection Document to remove the barrier between UNC and CAM NC compliance allowing full implementation of UNC 0755S and makes a minor change to clarify the Legal Text.

Timeline

Raised
Yes
07/01/2022
Status

Date modification raised

Panel Assessment
Unset
Workgroup Report Due
No
20/01/2022
Status

New Modification to be considered by Panel


Consultation
Unset
Consultation - Final Modification Report
No
20/01/2022
Status

Final Modification Report available for Panel


Panel Decision
Yes
20/01/2022
Status

Modification Panel decision

Implementation
Completed
24/04/2022