0730V - COVID-19 Capacity Retention Process

Last updated: 
9 August, 2023
Proposer
Steve Mulinganie
Modification type
Urgent
Status:
Rejected
 19/03/2021
Impact:
Low impact: Consumers
Medium impact: GB Gas Transporters, Independent Gas Transporters
High impact: Shippers

Allow sites (supply points) isolated in accordance with Modification UNC723 (Urgent) - Use of the Isolation Flag to identify sites with abnormal load reduction during COVID-19 period to be subject to a rebate of 50% of their LDZ Capacity Costs.

Timeline

Raised
Yes
07/10/2020
Status

Date raised

Panel Assessment
Unset
Workgroup Report Due
Unset
Consultation
Completed
06/07/2020
10/07/2020
Consultation - Final Modification Report
Yes
14/07/2020
Status

Final Modification Report available for Panel


Panel Decision
Yes
16/07/2020
Status

Modification Panel decision

Implementation
Unset