0690S - Reduce qualifying period for Class 1

Last updated: 
21 August, 2023
Proposer
Rhys Kealley
Modification type
Self-Governance
Status:
Implemented
 24/03/2020
Implementation date
Impact:
Low impact: Consumers, GB Gas Transporters, Independent Gas Transporters, National Gas Transmission
Medium impact: CDSP, Shippers

This Modification proposes that the qualifying period for the requirement for a meter point to become Class 1 is reduced, to limit the time period when very large sites are subject to NDM Demand Estimation, as opposed to being Daily Metered.

The Modification also proposes a new Performance Assurance report of sites which have met the qualifying criteria for Class 1 but are in Class 2, Class 3 or Class 4.

Timeline

Raised
Yes
16/10/2019
Status

Date raised

Panel Assessment
Unset
Workgroup Report Due
Yes
29/04/2019
Status

Initial consideration by Workgroup


Consultation
Completed
19/12/2019
23/01/2020
Consultation - Final Modification Report
Yes
30/01/2020
Status

Final Modification Report available for Panel


Panel Decision
Yes
20/02/2020
Status

Modification Panel decision

Implementation
Completed
25/03/2020