0687V - Creation of new charge to recover Last Resort Supply Payments

Last updated: 
21 August, 2023
Proposer
Andrew Green (Total Gas & Power Limited)
Modification type
Authority Direction
Status:
Rejected
 20/01/2022
Impact:
Low impact: CDSP
Medium impact: Distribution Network Operators
High impact: Shippers

To create a new charge, the SoLR Customer Charge, through which the Gas Distribution Networks (Transporters) will recover any Last Resort Supply Payments arising from a Supplier of Last Resort event .

Timeline

Raised
Yes
12/07/2019
Status

Date raised

Panel Assessment
Unset
Workgroup Report Due
Yes
10/05/2019
Status

Initial consideration by Workgroup


Consultation
Completed
15/08/2019
06/09/2019
Consultation - Final Modification Report
Yes
09/09/2019
Status

Final Modification Report available for Panel


Panel Decision
Yes
19/09/2019
Status

Modification Panel decision

Implementation
Unset