0618 - (Urgent) Extension of Invoicing Contingency Arrangements in case of Project Nexus defect

Last updated: 
11 August, 2023
Proposer
Richard Pomroy
Modification type
Urgent
Status:
Implemented
 22/03/2017
Implementation date
Impact:
High impact: GB Gas Transporters, Independent Gas Transporters, Rough Storage, Shippers

TPD Section S 1.9 allows for estimated invoices to be produced if the system cannot produce an invoice. This facility is limited to one month unless each User agrees to an extension and this modification proposes that this should be extended in the interests of ensuring that the liquidity of the industry is maintained.

Timeline

Raised
Yes
03/05/2017
Status

Date raised

Panel Assessment
Unset
03/05/2017
Status
Request for Urgency
Workgroup Report Due
Yes
10/05/2017
Status

Ofgem decision on Urgency


Consultation
Completed
10/05/2017
15/05/2017
Consultation - Final Modification Report
Yes
16/05/2017
Status

Final Modification Report available for Panel


Panel Decision
Yes
18/05/2017
Status

Modification Panel recommendation

Implementation
Unset
01/06/2017